Ontario Refurbishing Hydroelectric Station in Cornwall

May 22, 2024

Ontario Refurbishing Hydroelectric Station in Cornwall

R.H. Saunders Generating Station will supply reliable, affordable and clean power for decades to come

The Ontario government is supporting Ontario Power Generation’s (OPG) plan to refurbish its R.H. Saunders Generating Station in Cornwall, the second largest hydroelectric station in Ontario. This infrastructure program would invest more than $600 million to secure 1,045 megawatts (MW) of clean electricity, equivalent to powering over one million homes, helping to meet increasing demand from electrification and fueling the province’s growth.

“The R.H. Saunders Generating Station – the second largest hydro facility in the province – has been providing Ontario with clean electricity since 1958, and with today’s investment, we’re extending the life of the station for decades more to help Ontario meet its growing electricity needs,” said Todd Smith, Minister of Energy. “This refurbishment program – part of our Powering Ontario’s Growth plan – will create jobs and ensure we have the power we need for the next major international investment, the new homes we are building and industries as they grow and electrify.”

OPG will refurbish 16 units in total at the R.H. Saunders Generating Station. The refurbishment will include major rehabilitation of generating equipment through civil, electrical, and mechanical improvements that will see the station produce more electricity from less water. Once completed, the station is expected to produce up to 160 gigawatt hours of additional clean electricity each year, equivalent to powering over 19,000 homes.

The work at the R.H. Saunders Generating Station will take place over the next 16 years, creating more than 200 highly skilled and well-paid jobs in Cornwall.

“Since it first went into service in 1958, OPG’s R.H. Saunders station has played an important role in Ontario’s history. From powering a growing economy to managing flows in the St. Lawrence Seaway for shipping, this hydro stalwart has been invaluable to our province.” said Paul Seguin, Senior Vice President, Renewable Generation, OPG. “Once refurbished, it will electrify the lives of Ontarians for years to come.”

This investment in Ontario’s hydroelectric fleet is just one part of Powering Ontario’s Growth, the government’s pragmatic plan which outlines the actions the province is taking to meet growing energy demand and reduce emissions by expanding Ontario’s reliable, affordable and clean grid, including:

Quick Facts

  • Ontario’s grid is one of the cleanest in the world with a diverse supply mix made up of nuclear, hydroelectric, natural gas, wind, solar and bioenergy.
  • The R.H. Saunders Generating Station has been a reliable source of clean power for 65 years. The station currently meets about five per cent of Ontario’s power needs.
  • The R.H. Saunders Generating Station is located on the St. Lawrence River as part of the larger Moses-Saunders Power Dam shared with the United States.

Quotes

“Through the revitalization of OPG’s R.H. Saunders Generating Station, we’re not just renewing infrastructure; we’re fortifying Ontario’s energy future. This project stands as a testament to our commitment to sustainable, dependable power, ensuring generations ahead benefit from the legacy of clean energy.”

– MPP Nolan Quinn

“The City of Cornwall welcomes the province’s investment in the R.H. Saunders Generating Station. This refurbishment project will ensure that the facility is able to continue to provide clean energy for decades to come, while also creating hundreds of skilled jobs in our community.”

– Mayor Towndale

Source

Related Story

Ontario Refurbishing Hydroelectric Stations in Niagara

The Ontario government is supporting Ontario Power Generation’s (OPG) plan to refurbish its hydroelectric stations in the Niagara region, including the Sir Adam Beck Complex at Niagara Falls. This $1 billion dollar infrastructure program would secure up to 1,700 megawatts (MW) of clean electricity, equivalent to powering 1.7 million homes, helping to meet increasing demand from electrification and fueling the province’s growth.

Related Articles


Latest Articles

  • Lighting Up the Quantum Computing Horizon with Aurora

    January 28, 2025 A peek inside Xanadu’s latest and greatest photonic quantum computer—Aurora. By Zachary Vernon The Xanadu team has recently announced the successful completion of Aurora, their latest photonic quantum computer. This machine follows in a line of successively more sophisticated earlier systems demonstrations, including X8 and Borealis. Both of those were ground-breaking in their own right: X8 brought… Read More…

  • Guide to Mechatronics – Part 7: Challenges and Problem-Solving in Mechatronics

    January 27, 2025 The field of mechatronics, while innovative and dynamic, comes with its own technical and integration challenges. These challenges often stem from the interdisciplinary nature of mechatronic systems and the complexity of blending mechanical, electronic, and computational elements into a cohesive unit. Technical Challenges Integration Challenges Problem-Solving Approaches Addressing these challenges requires a… Read More…


Featured Article

Revolutionizing Material Movement with Autonomous Mobile Robots

Revolutionizing Material Movement with Autonomous Mobile Robots

In today’s fast-paced manufacturing and logistics industries, the need for efficient and flexible material movement solutions has never been greater. Traditional methods like conveyor systems, forklifts, and manual pushcarts have served us well, but they come with limitations.

That’s why Omron is thrilled to announce the launch of their game-changing MD Series of Autonomous Mobile Robots (AMRs). Read more


Products

  • Teledyne FLIR Launches Prism Supervisor Software, Enhances UAS Autonomous Capabilities

    January 31, 2025 Prism Supervisor integrates drone autopilot flight control systems with real-time, AI-based observations Teledyne FLIR OEM, part of Teledyne Technologies Incorporated, recently announced the release of Prism™ Supervisor, the latest addition to its Prism embedded software ecosystem. Prism Supervisor integrates drone autopilot flight control systems with real-time, AI-based observations at the edge to improve… Read More…

  • Teledyne FLIR SIRAS Professional Drone is Now Available in Canada

    January 31, 2025 Teledyne FLIR SIRAS Professional Drone is Now Available in Canada Teledyne FLIR (part of Teledyne Technologies Incorporated) has announced that, for the first time, the Teledyne FLIR SIRAS™ professional uncrewed aerial system (UAS) will be available across Canada. This is being made possible through Rocky Mountain Unmanned Systems (RMUS). The SIRAS professional drone is designed for professional missions,… Read More…